July 28, 2000, E.C.B. No's. 30/93/187 (70 L.C.R. 126), 32/93/187
Between: |
Albert
Cecil Ingham and Lillian Rose Ingham
Russel Kowalski in his Capacity as Executor for
the
Estates of Samuel Kowalski and Helen Kowalski
Claimants |
And: |
Town
Of Creston
Respondent |
Before: |
Julian
K. Greenwood, Presiding Member
Michael Grover, AACI, Board Member
Lesley Eames, AACI, Board Member |
Appearances: |
Reinhard
Burke, for the Claimants
J. Bruce Melville, for the Respondent |
REASONS FOR DECISION ON RECONSIDERATION
1. INTRODUCTION
This case involved a street widening in Creston, British
Columbia, resulting in the expropriation of a 16½ foot
strip of land along one side of Hillside Street. The
owners of three properties affected by the expropriation
brought compensation claims which were heard together.
The board issued a decision on June 25, 1996 (59 L.C.R.
113) in which it made findings on each property on claims
for the market value of land taken, disturbance damages,
personal losses, and (since these were partial takings
only) loss of market value to the remainders of each
parcel.
The owners of two of the properties, the Inghams and
Mr. Kowalski, brought an appeal of this decision to
the Court of Appeal for B. C. The grounds of appeal
were as follows:
1. |
The Board erred
in construing s. 43 (now s. 44) of the Expropriation
Act, R.S.B.C. 1996, c.125, in finding that
general benefits should be deducted from the compensation
awarded. |
2. |
The Board erred
in construing s. 971 (now s. 912) of the Municipal
Act, R.S.B.C. 1996, c. 323, as having the
effect of ensuring that no loss to the remaining
lands can occur where a partial taking results
in the remaining lands failing to conform with
a zoning bylaw. |
3. |
The Board erred
in its method of calculating the reduction in
the market value of the remaining lands. |
The Court of Appeal issued its decision on March 22,
1999 (66 L.C.R. 161). The Court held that the board
had erred when it used a post-taking sale of the Kowalski
property that was directly affected by the road widening
as the basis for an "after value", which was
then used in a "before and after" method for
determining the value of the taking and the loss in
value to the remaining lands.
In this decision the Court of Appeal agreed with the
appellants (claimants) that by the board's use of the
sale of one of the affected properties to support the
"after" value, it incorporated into the conclusion
of compensation general benefits which may have accrued
to all the property owners on Hillside Street from the
project. The appellants argued that, while special benefits
to a property may be deducted from an award, under then
s. 43 of the Act (now s. 44 amended), general
benefits may not. At that time, sections 40(1) and 44(1)
of the Expropriation Act provided:
40
(1) |
Subject to section
44, if part of the land of an owner is expropriated,
he or she is entitled to compensation for |
|
(a) the reduction
in market value to the remaining land, and |
|
(b) reasonable
personal and business losses |
|
that are directly
attributable to the taking or that result from
the construction or use of the works for which
the land is acquired. |
44
(1) |
If part of the
land of an owner is expropriated, and the construction
or use of works by the expropriating authority
are of special benefit to that owner or to his
or her remaining land beyond any general benefit
to any other owner benefited by the construction
or use, there must be deducted from the amount
of compensation payable to that owner the estimated
value of the benefit. |
The Court accepted the appellants' submission that
the approach used by this board necessarily resulted
in general benefits, available to any property owner
on the street, being deducted from the award. The parties
were generally agreed that there were no "special
benefits" to the Ingham and Kowalski properties.
Thus the first and third ground of appeal succeeded.
The Court did not consider it necessary to rule on the
second ground of appeal.
In its June 1996 decision, the board had awarded compensation
under the heading of "reduction in market value
to the remaining land" of $5,075 for Ingham and
$4,400 for the Kowalski property, in addition to the
value of the land taken. The Court of Appeal ordered
that "the parties ought to be given an opportunity
to consider, in view of the relatively small amounts
involved and the considerable expense entailed in further
proceedings before the Board, to agree on the awards
to be substituted by this Court for those made by the
Board." The parties were not able to agree and
subsequently the Court of Appeal made a supplementary
order (1999 BCCA 316) remitting the matter back to the
Expropriation Compensation Board "to be determined
in accordance with [this Court's] reasons ...".
This board held a one day hearing into the reconsideration
on November 3, 1999.
Between the date of the Court of Appeal decision and
this reconsideration, the provisions of the Act
regarding general and special benefits were amended
by the Miscellaneous Statutes Amendment Act (No.
3), S.B.C. 1999, c. 39, as follows:
13) |
Section
44 is amended |
|
(a) |
in subsection
(1) by adding "the expropriation or"
before "the construction or use" in
both places, and |
|
(b) |
by adding the
following subsection: |
|
|
(1.1) If part
of the land of an owner is expropriated, and the
expropriation or the construction or use of the
works for which the expropriated land was acquired
are of any benefit to that owner, the estimated
value of the benefit must be deducted from the
amount of compensation otherwise payable to that
owner, under section 40 (1) (b) (i), for the
reduction in the market value of the remaining
land, whether or not any other owner is benefited
by the expropriation of the expropriated land
or by the construction or use of the works. (emphasis
added) |
We are not, however, bound to follow the revised section
for this determination because the Miscellaneous
Statutes Amendment Act (No. 3) includes a transitional
provision for cases currently under adjudication:
79) |
Sections
40 and 44 of the Expropriation Act, as
amended by this Act, apply to any compensation
claimed or payable in respect of any expropriation,
whether or not that expropriation occurred before
the coming into force of this section, unless,
before the coming into force of this section, |
|
(a) |
a court order
had been made respecting compensation payable
under the Expropriation Act in respect
of the expropriation, or |
|
(b) |
a determination
had been made of the compensation payable under
that Act in respect of the expropriation. |
Of the three parties to the original compensation claim,
only the Inghams and Mr Kowalski brought the appeal
and these are therefore the only properties subject
to this reconsideration.
2. SCOPE OF RECONSIDERATION
2.1 No new evidence
A preliminary issue was the proper scope of the reconsideration.
The respondent had filed new appraisal reports that,
by their titles, purported to value the reduction in
value to the remaining portions of each of the Kowalski
and Ingham properties. Mr. Burke, counsel for the claimants,
objected to the admission of these reports. He took
the position that the board was not engaged in a full
rehearing, but rather that it was confined by the Court
of Appeal's order to a reconsideration of the existing
evidence. The board decided not to receive the reports,
although not quite for the reasons urged on it by Mr.
Burke. It held that the Court of Appeal's order did
not bind it to proceed without new evidence; the board
had a discretion. However it
would in any event exercise its discretion not to receive
new evidence. In the board's view, it was in much the
same position as it would have been if the hearing had
closed, but that a decision (on these particular issues)
had yet to be issued. It was not appropriate to take
further evidence on an issue that had at all times been
squarely before the board, and on which the respondent
had taken a firm position both in its pleadings and
in argument.
2.2 Loss in value to the remaining lands
The reconsideration was also limited in its subject
matter. The Court of Appeal had only vacated those aspects
of the decision which dealt with the claims for reduction
in value to the remaining lands. All other decisions
remained in place. The board was therefore only to reconsider
its awards for loss in value to the remainder properties.
2.3 Loss of conformity
Another argument made to the Court of Appeal was that
the board had erred in its treatment of a certain section
of the Municipal Act. That section (formerly
s. 971, now s. 912) provides that if a partial taking
results in nonconformance with a zoning bylaw the remainder
is nevertheless "deemed to conform", unless
compensation is paid to the owner for the loss of conformity.
The board had decided not to award compensation for
such a loss, on the ground that this deeming clause
would then take effect, and that the properties would
still be in (deemed) conformity. On appeal, it was argued
that the board should have made an award for non-conformity
in the case of Kowalski. However the Court of Appeal,
while declining to rule whether the board was correctly
interpreting the section, nevertheless agreed with the
board's ruling that the section "does not determine
whether the Board should or should not award compensation
for non-conformity". The Court therefore made no
ruling on this ground of appeal.
On this reconsideration, Mr. Burke argued that the
board ought to revisit its decision on non-conformity
on the ground that the "deemed conformity"
status of the Kowalski property may nevertheless have
some impact on its remainder value. This therefore was
a factual question which he urged the board to reconsider.
The board does not see any reason to depart from its
original reasoning on this issue. We have essentially
no useful evidence on what the loss of value expressly
related to nonconformity, if any, would be in the Kowalski
case, yet if we award even $1.00 in that respect, the
Kowalski property would lose its deemed conformity status.
If Mr. Burke is asking us to make an award for "deemed
conformity" as opposed to true conformity, we have
absolutely no evidence on which to do so. We prefer
not to make any award.
3. REDUCTION IN MARKET VALUE TO THE REMAINING LAND
3.1 Method of Measurement
The Court of Appeal has criticized the board's use
of the "before and after" method as a measurement
of the reduction in value created by the project, because
the board failed to screen out general benefits, if
any, accruing to properties on Hillside Street from
the road improvement. The problem is not with the method
itself, but with the fact that the only direct market
evidence of "after" value was the sale of
the Kowalski property, 17 months after the expropriation.
Both parties took the position that to avoid the problem
identified by the Court, the board should not use the
before and after method, and should look for an alternate
way of measuring the reduction in value to the remaining
lands, under s. 40(1)(a). We are left with two possible
methods:
a. |
Adopting the Cost
Approach to measure depreciation caused by the
taking, as it was used by the claimants' appraiser,
Danny Grant. For the Kowalski property, Mr. Grant
estimated the cost of certain remedial measures,
such as the use of additional insulation and triple
glazing in windows and proposed a further 5% reduction
of the total property value for non-curable loss.
For the Ingham property, he was of the opinion
that a new bedroom addition on the rear of the
house would be necessary to restore the property
value. |
b. |
Estimating an
overall loss from all causes, reflected as a percentage
of the building value, based on the best available
evidence. |
Claimants' counsel, Mr. Burke, urged us to use Mr.
Grant's approach citing several cases using this type
of measure of reduction in value to remaining land caused
by a partial taking.
There are some intrinsic difficulties with the first
approach. We expressed in our previous decision our
doubt that the mitigation costs, as Mr. Burke has called
them, would in the general case be good evidence of
the loss of market value. Some items of proposed mitigation,
such as Mr. Grant's rather extreme suggestion that a
300 square foot addition be added to the Ingham house,
would increase the value of the overall property, raising
the issue of betterment.
Mr. Melville, counsel for Creston, argued that the
board should be measuring the market value impact and
that this was not necessarily the cost of reinstatement.
The board does note, however, that at the original hearing
Creston did not put in any independent evidence of a
reduction in market value, preferring simply to criticize
the claimants' expert reports.
An additional technical difficulty is that mitigative
expenses, to the extent that they exceed any actual
loss of value to the remainder, would have to be recoverable
under a different head of compensation – presumably
as disturbance damages. Yet the Court of Appeal has
clearly not opened those other aspects of our decision.
We will therefore attempt to restrict ourselves to the
loss of value to the remainders of the properties, no
matter how difficult that may be.
The board does not wish to be taken, by these comments,
as agreeing that the claimants have actually suffered
disturbance damages in the amounts claimed through the
calculations of "mitigative expenses" presented
by Mr. Grant. In large part they had not in fact incurred
such expenses, and had they incurred them, there would
always remain a question of their reasonableness. In
this decision, we simply observe that we are neither
required nor permitted to reconsider such heads of damage.
3.2 Analysis
We are not at all satisfied with the quality of the
alternative evidence offered. Nevertheless, as has been
said in other cases, we must do the best with what we
have. The only other evidence is Mr. Grant's opinion
that reduction of value to the remainder, at least as
to the "incurable" component, might be measured
by a percentage of value before the scheme.
Mr. Grant's opinion of the percentages we should use
for the incurable component of loss ranged quite widely.
He referred to studies conducted by his firm from other
situations of various types; relying particularly on
studies related to the widening of high-traffic roads
in the Lower Mainland. These led him to propose initially
that impacts could lie in a range of 0% to 30% of total
value (of the remainder value "before" the
scheme). On Hillside Street in Creston, he recognized
that the impact should be lower, and proposed a range
between 0% and 10%.
In the end, Mr. Grant proposed for the Kowalski property
$7,750 for curable items and 5% of the overall residual
value for incurable loss. This resulted in a total loss,
in his opinion, of $11,733. For the Ingham property
he argued that the loss should be measured by the cost
of constructing an additional bedroom, less an estimate
of betterment. This produced a net cost of $15,745.
Grant's conclusions amounted to 23% and 31% of the building
values, respectively.
The board feels that these percentages are too high.
Grant has overstated the effect of the road widening.
While the houses are now closer to the street and faced
with the potential of increased traffic volume, the
impact on value should not be compared with the impact
of a freeway. The board also is reminded that the Inghams
and Mr. Kowalski received compensation for landscaping
to replace trees and shrubbery taken. Such replacement
landscaping would reduce any impact of greater exposure
to traffic, including the particular impact on the Ingham
property of headlights shining into the bedroom window.
For the question of betterment to be properly applied,
it would be necessary to go beyond Mr. Grant's somewhat
rudimentary approach of merely depreciating the new
component at the same rate as the old dwelling. On his
figures, the claimant would be faced with a cost new
of $23,248, an added value (by depreciated cost) of
$7,503, and hence a claimed sum – which he calls a net
cost – of $15,745. Whether such an addition would enhance
value, and if so by how much, was not tested; whether
it might extend the life of the dwelling was not broached;
whether the claimant was being reasonable in pursuing
claims for remediation costs was not addressed. In this
case, the supposed betterment of $7,503 is neither supported
by reference to the market nor can it be said to be
reasonable as a consequence of increasing the depreciated
cost from $50,753 to $58,256 from an outlay of $23,248.
The evidence of the Town Administrator, which the board
accepts, was that the taking had resulted in certain
reduced setbacks – the distances from the new front
property line to the houses. In the case of the Ingham
house which is configured in an L-shape, the bedroom
is now 15 feet from the property line, whereas the family
room is setback by 33 feet. In the case of the Kowalski
house, the front of the house containing two bedrooms
and the living room is 20½ feet from the property line.
These measured distances are quite different from Mr.
Grant's estimates. Mr. Grant reported the Ingham house
as being about 28 feet from the sidewalk to the living
room and the bedroom as being 17 feet back from the
road. Yet the living room, according to his plan, is
set back 18 feet from the bedroom. He shows the Kowalski
house as being about 10 to 12 feet from the sidewalk.
This is consistent with his report. He testified that
the setback was six feet from the porch to the edge
of the sidewalk. In neither case did Mr. Grant provide
measured distances from the new property line to the
dwelling.
The board has more confidence in the dimensions as
measured by the Town officials, that were not challenged
at the hearing, rather than the estimates reported by
Mr. Grant. The Town's evidence shows the Ingham bedroom
as being 5½ feet closer to the new property line than
are the two Kowalski bedrooms. The Ingham living room
is 12½ feet further back from the street than the Kowalski
house. While both properties are likely worth less on
these accounts, in the view of the board both have suffered
to about the same extent.
The board prefers to measure the impact as a percentage
of building value, rather than as a percentage of the
total remainder value, since the complaint is that the
useability of the buildings as residences have been
impaired. The unimpaired values of the two buildings
are the depreciated cost estimates provided by Grant.
4. CONCLUSION
Having had the benefit of photographs before and after
the project, a site visit that was helpful to the board
in placing some of the issues in context, and all the
evidence before us we find a reduction in value to the
Kowalski property to be 15% of the building value, estimated
by Grant to be $50,276, for a reduction of $7,541. Recognizing
a similar effect for the Ingham property, we find a
reduction in the remainder value of that property to
be 15% of the building value of $50,753, or $7,613.
5. INTEREST AND COSTS
In considering the issue of costs, the board is mindful
of the observations of the Court of Appeal regarding
the expense of bringing this matter before another sitting
of the board given the small amounts involved, granting
the claimants each just over $2,500 further compensation.
We do, however appreciate the position of the claimants
and their success before the Court of Appeal. We also
recognize that counsel expedited the time for re-hearing
the matter, keeping the submissions to a one day sitting.
We therefore find no reason to change the earlier decision
that interest should run from the date of expropriation,
with additional interest as permitted by the statute
and that the claimants are entitled to their reasonable
costs in the meaning of the Act, including the
additional costs of and related to one additional day
of hearing and reconsideration.
To the extent that costs are incurred after the date
of introduction of the new Tariff, the board grants
costs on Scale 2.
THEREFORE IT IS ORDERED THAT
The Town of Creston shall pay to the claimants:
(1) |
Compensation
pursuant to section 40(1) of the Act for
the reduction in market value to the remaining land,
a total of $7,541 to Russel Kowalski, as executor
for Samuel Kowalski and Helen Kowalski; |
(2) |
Compensation
pursuant to section 40(1) of the Act for
the reduction in market value to the remaining land,
a total of $7,613 to Albert Cecil and Lillian Rose
Ingham. |
(3) |
Interest
on the awards pursuant to section 46 of the Act
from August 19, 1992 until paid, with adjustments
to take into account moneys paid by the Town to
the claimants. Pursuant to section 46(2) of the
Act interest shall be calculated at the following
rates: |
|
a) |
Seven per cent (7.00%)
from August 19, 1992 to December 31, 1992; |
|
b) |
Seven and one-quarter
percent (7.25%) from January 1, 1993 to June 30,
1993; |
|
c) |
Six per cent (6.00%)
from July 1, 1993 to December 31, 1993; |
|
d) |
Five and one-half
per cent (5.5%) from January 1, 1994 to June 30,
1994; |
|
e) |
Eight per cent (8.00%)
from July 1, 1994 to December 31, 1994; |
|
f) |
Eight per cent (8.00%)
from January 1, 1995 to June 30, 1995; |
|
g) |
Eight and three-quarters
per cent (8.75%) from July 1, 1995 to December 31,
1995; |
|
h) |
Seven and one-half
per cent (7.5%) from January 1, 1996 to June 30,
1996; |
|
i) |
Six and one-half
percent (6.5%) from July 1, 1996 to December 31,
1996; |
|
j) |
Four and three-quarters
per cent (4.75%) from January 1, 1997 to June 30,
1997; |
|
k) |
Four and three-quarters
per cent (4.75%) from July 1, 1997 to December 31,
1997; |
|
l) |
Six per cent (6.00%)
from January 1, 1998 to June 30, 1998; |
|
m) |
Six and one-half
per cent (6.5%) from July 1, 1998 to December 31,
1998; |
|
n) |
Six and three-quarters
per cent (6.75%) from January 1, 1999 to June 30,
1999; |
|
o) |
Six and one-quarter
per cent (6.25%) from July 1, 1999 to December 31,
1999; |
|
p) |
Six and one-half
per cent (6.5%) from January 1, 2000 to June 30,
2000; |
|
q) |
Seven and one-half
per cent (7.5%) from July 1, 2000 to December 31,
2000. |
(4) |
Additional
interest pursuant to section 46(4) of the Act,
from the dates of the advance payments, at a rate
of five per cent (5.00%) per annum to the date of
this decision. |
(5) |
Pursuant
to section 45 of the Act, 100% of the claimants'
actual reasonable legal, appraisal, and other costs
for the purpose of asserting their claim for compensation
until June 28, 1999 and costs according to the Tariff
on Scale 2 after that date. |
|