B.C. Reg. 263/2021, deposited October 13, 2021, under the UTILITIES COMMISSION ACT [section 22]. Ministerial Order M386/2021, dated October 12, 2021.

I, Bruce Ralston, Minister of Energy, Mines and Low Carbon Innovation, order that the attached Shulus Exemption Regulation is made.

— B. RALSTON, Minister of Energy, Mines and Low Carbon Innovation.

SHULUS EXEMPTION REGULATION

Definitions

1 In this regulation:

"Act" means the Utilities Commission Act;

"Kingsvale pump station" means the pump station owned and operated by Trans Mountain Corporation in Kingsvale, south of the City of Merritt, and supplied by the Kingsvale transmission line;

"Kingsvale transmission line" means the approximately 24 km, 138 kV transmission line located south of the City of Merritt that connects the Kingsvale pump station to the authority's transmission system at circuit 1L251 and is designated by the authority as 1L251KPS;

"Shulus" means the Shulus Electricity Transmission LP.

Exemption

2 (1) Shulus is exempt from Part 3 of the Act in respect of

(a) its ownership and operation of the Kingsvale transmission line, and

(b) the provision of service respecting the transmission of electricity from the authority's transmission system to the Kingsvale pump station.

(2) Despite subsection (1), Shulus is not exempt from section 42 of the Act in relation to orders of the Commission respecting safety issued to Shulus under section 23, 25, 37 or 49 of the Act.